Client:
Fraser Coast Regional Council
Contract Value:
circa $1.4m
Location:
Fraser Coast Region
Completion:
March, 2022
Scope of Works:
The project extended to the intersection with Pialba-Burrum Heads Road (a state controlled road). The length of road to be reconstructed as approximately 1150 metres with a 100km/h sped limit. The works improved the vertical alignment of the road as well as increased pavement widths. Co-ordination of relocation of power poles. Re-establishment of Permanent Survey Marker on redundant culverts in accordance with the Survey and Mapping Infrastructure Act.
The extent of work involved
- Earthworks
- Pavement construction
- Stormwater drainage upgrades
- Rural access upgrades
- Barrier kerb installation at both intersections
- Table drain reformation.